VDOT IMPROVES PERFORMANCE WITH DELIVERING PROJECTS ON TIME AND ON BUDGET


RICHMOND - The Virginia Department of Transportation (VDOT) latest
quarterly report released today shows a growing trend in delivering more construction and maintenance projects on time and on budget.

“We continue to improve our performance by following three key principles - set goals, measure performance and be accountable,” said VDOT Commissioner Philip Shucet. “All lead to sustainable improvements.”

Construction contracts:

*Contracts completed on timeContracts completed within budget
FY 2001 – 20%51 %
FY 2004 – 36%73%
FY 2005 – On target to complete 60% of contracts on deadline, and 80% within budget

*On time means finishing a project on or before the original date what VDOT contracted for, no exceptions.

64% of contracts were completed within 90 days of the original completion date in 2004 compared with 53% in 2003.

Maintenance contracts:

Contracts completed on deadlineContracts completed within budget
FY 2001 – 38%59%
FY 2004 – 51%81%
FY 2005 – On target to complete 70% of contracts on deadline and 90% within budget.