FINAL CONSTRUCTION WORK UNDERWAY ON FALL HILL AVENUE PROJECT
Motorists can anticipate single lane closures and travel delays in late March, April on Interstate 95, Route 1, Fall Hill Avenue, and Mary Washington Boulevard in Fredericksburg

FREDERICKSBURG – As construction nears completion on the Fall Hill Avenue widening and Interstate 95 overpass replacement project in Fredericksburg, motorists may encounter daytime and overnight lane closures in the work zone through late April for milling, paving, pavement marking and other final tasks.

Next week, lane closures are scheduled weather permitting at the following locations:

Interstate 95 Southbound at mile marker 131 (Fall Hill Avenue)

Wednesday, March 29 ˗˗ Thursday, March 30

  • Single lane closure at 9:30 p.m.
  • Double lane closure at 10 p.m.
  • All lanes reopen to traffic by 5 a.m.

Route 1 Northbound, Southbound at Mary Washington Boulevard

Sunday, March 26

  • Single lane closure in both directions 10 p.m. ˗˗ 6 a.m.

Monday, March 27 ˗˗ Tuesday, March 28

  • Single lane closure in both directions 6 p.m. ˗˗ 6 a.m.

Wednesday, March 29 ˗˗ Thursday, March 30

  • Single lane closure on Route 1 northbound only, 6 p.m. ˗˗ 6 a.m.

Fall Hill Avenue from Gordon Shelton Boulevard to Rappahannock Canal

Monday, March 27 − Thursday, March 30

  • Intermittent single lane closures 9 a.m. – 3 p.m.

Friday, March 31

  • Intermittent single lane closures 9 a.m. – noon.

Project Background

Construction began in February 2015 to widen Fall Hill Avenue to four lanes with a raised median from Carl D. Silver Parkway to just west of the bridge over the Rappahannock Canal. The project is also extending Mary Washington Boulevard to connect with Fall Hill Avenue in a roundabout, west of the Rappahannock Canal bridge.

Work is scheduled to be completed by April 20, 2017.

Additional project details can be found online at www.VirginiaDOT.org on the project page.

511Virginia

Motorists can find real-time information on lane closures, work zones, traffic and other incidents on 511Virginia.

Download the  free mobile 511Virginia app for Apple and Android devices to stay connected, or visit www.511Virginia.org. Motorists also can reach 511Virginia by calling 511 from any phone in Virginia.

(END)

 

VDOT’s 14-county Fredericksburg District includes the counties of Caroline, King George, Spotsylvania and Stafford in the Fredericksburg area; Northumberland, Richmond, Lancaster and Westmoreland counties in the Northern Neck; Essex, Gloucester, King & Queen, King William, Mathews and Middlesex counties in the Middle Peninsula.

 

 

 



Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.

Page last modified: March 24, 2017