Rt 110 Nighttime Lane Closures at Rt 27 Rescheduled
Full closures up to 30 minutes for bridge beam placement

ARLINGTON – Due to inclement weather last week, nighttime closures along Route 110 at the Route 27 interchange and local ramps in order to install bridge beams have been rescheduled, according to the Virginia Department of Transportation.

The updated closure schedule is as follows, weather permitting:

  • Monday night, Aug. 14 and Tuesday night, Aug. 15: Two left lanes of southbound Route 110 closed between 10 p.m. and 5 a.m., full closures up to 30 minutes each on northbound Route 110 between 11:30 p.m. and 4 a.m.
  • Wednesday night, Aug. 16 & Thursday night, Aug. 17: Two left lanes of northbound Route 110 closed between 10 p.m. and 5 a.m., full closures up to 30 minutes each on southbound Route 110 between 11:30 p.m. and 4 a.m.
  • Friday night, Aug. 18, Saturday night, Aug. 19, Monday night, Aug. 21 and Tuesday night, Aug. 22: Right lane of southbound Route 110 closed between 10 p.m. and 5 a.m., closures up to 30 minutes each on ramp from westbound Route 27 to the Pentagon between 10 p.m. and 5 a.m.
  • Wednesday night, Aug. 23 and Thursday night, Aug. 24: Full closures up to 30 minutes each on both northbound and southbound Route 110 between midnight and 4 a.m.
  • Friday night, Aug. 25: Two right lanes of northbound Route 110 closed between 10 p.m. and 5 a.m., closures up to 30 minutes each on ramp from eastbound Route 27 to northbound Route 110 between 10 p.m. and 5 a.m.
  • Saturday night, Aug. 26: Two right lanes of southbound Route 110 closed between 10 p.m. and 5 a.m., closures up to 30 minutes each on ramp from westbound Route 27 to the Pentagon between 10 p.m. and 5 a.m.

Drivers should expect delays and are advised to use alternate routes. Message signs alerting motorists to the closures are in place.

The work is part of the Route 27 over Route 110 project, which is scheduled for completion in spring 2018.