RELEASE:

CONTACT:
IMMEDIATE

Mike Murphy 703-259-1757
703-638-8547 michael.murphy@vdot.virginia.gov
NR18-009

Jan. 26, 2018



Route 27/110 Nighttime Closures Jan. 29 - Feb. 3
Full closures along westbound Route 27 during bridge deck work

ARLINGTON – The Route 27 and Route 110 interchange will have nighttime closures, weather permitting, Monday night, Jan. 29 through Saturday night, Feb. 3 for bridge deck work, according to the Virginia Department of Transportation.

The closures will occur according to the following schedule:

  • Monday night, Jan. 29 and Tuesday night, Jan. 30: Westbound Route 27 full closures up to 30 minutes each between midnight and 4 a.m. each night; westbound Route 27 single-lane closures between 10 p.m. and 5 a.m. each night; northbound and southbound Route 110 multiple lane closures between 10 p.m. and 5 a.m. each night; ramp closed from eastbound Route 27 to northbound Route 110 between 10 p.m. and 5 a.m. each night (traffic will be detoured via Route 27, George Washington Memorial Parkway and I-395 back to Route 110).
  • Wednesday night, Jan. 31, Thursday night, Feb. 1, Friday night, Feb. 2 and Saturday night, Feb. 3: Westbound Route 27 full closures up to 30 minutes each between midnight and 4 a.m. each night; westbound Route 27 single-lane closures between 10 p.m. and 5 a.m. each night; northbound and southbound Route 110 multiple lane closures between 10 p.m. and 5 a.m. each night

The work is part of the Route 27 over Route 110 project, which is scheduled for completion this summer.

Follow VDOT Northern Virginia on Twitter: @vadotnova

                                                                                              END



Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.

Page last modified: Jan. 26, 2018