In Design

Corridor Q: Route 460/121 Poplar Creek Phase A

Project at a Glance

Locality
Buchanan

District
Bristol

Contact
Robert Cumbow, Project Manager
276-889-7676

What's being done?

VDOT's $167 million design-build contract for the Corridor Q: Route 460/121 Poplar Creek Phase A section is underway and includes design and construction of a 2.8-mile section of new highway in Buchanan County.

Bizzack Construction, LLC, is the design-build contractor for the project and 3B Consulting Services, LLC, is the design-build lead designer for the project.

Route 460/121 Poplar Creek Phase A will travel from the east end of Route 460/121 Hawks Nest section to Route 604 (Poplar Creek Road).

A design public hearing for Route 460/121 Poplar Creek Phase A was held Tuesday, June 27 at Riverview Elementary School in Grundy.

Attached are the project advertisement, the design public hearing brochure and the design public hearing comment sheet.

Other Public Hearing Documents:

- Public hearing plans

- Public hearing plans, Route 604 detail

- Detour for relocated Route 604 construction Phase I construction

- Detour for relocated Route 604 construction Phase 3 construction

- Detour for relocated Route 615 construction

Background

In February 2015, the Commonwealth Transportation Board approved the location of Alternative F1 Modified for US Route 121 Section IIIB, which extends from east of the Route 460/121 Hawks Nest section to Grundy. In July 2015, the Federal Highway Administration (FHWA) also approved the location of Alternative F1Modified and indicated that the project could proceed to subsequent development.  Based on construction cost analyses, Corridor Q/Section IIIB Overlap has been split into two phases (A and B).  VDOT’s Central Office environmental section conducted a Reevaluation of the social, economic, and environmental impacts of Corridor Q Overlap (Poplar Creek) Phase A on the local community and surrounding area.  On April 19, 2017, FHWA determined that the construction of the project will not result in any new significant impacts and that the project may proceed to subsequent development.  Corridor Q Overlap Phase B will be advanced and be the subject of a separate environmental
re-evaluation when funding is identified.

Documents


Reevaluation for Corridor Q Overlap Phase A

Indirect and Cumulative Effects Technical Memo

Natural Resources Technical Memorandum

Socioeconomics, land use, and right of way relocations technical memorandum

Traffic Technical Memorandum

 

February 7, 2017 Meeting Brochure

Comment Sheet (submit to VDOT by February 25, 2017)

Fifth Amendment to the Assignment and Assumption Agreement dated July 6, 2016