I-95 Bridge Rehabilitation: Stafford and Spotsylvania

Project at a Glance

Begin Date
Fall 2016

Est Completion Date
November 2018

Phase
Under Construction

Cost
$6.6 million

Contractor
Fort Myer Construction Corp.

Locality
Spotsylvania and Stafford

District
Fredericksburg

Contact
Kelly Hannon, VDOT Communications Manager
(540) 374-3344
Darragh Copley Frye, VDOT Communications Coordinator
(540) 899-4119

Project Overview

Six bridges on Interstate 95 in Stafford and Spotsylvania counties will be rehabilitated during a two-year project.

The project will improve the condition of northbound and southbound bridges that carry I-95 over Aquia Creek and Potomac Creek in Stafford, and the Ni River in Spotsylvania.

Work will include deck repairs, superstructure repairs and substructure and crack repairs.

The project will also include installing dry rip rap, complete joint reconstruction, milling concrete decks, patching and installing a latex modified concrete on deck.

Construction began October 28, 2016 and is scheduled to be complete in early November 2018.

Work is anticipated to occur on the following schedule:

  • Ni River bridges (mile marker 121): Fall 2016-Spring 2017
  • Potomac Creek bridges (mile marker 137, just north of Exit 136/Centreport Parkway): Fall 2017-Spring 2018
  • Aquia Creek bridges (mile marker 145, just north of Exit 143/Route 610): Summer 2018-Fall 2018

To lessen the impact on traffic, most lane closures on I-95 will occur overnight and during off-peak hours

 