Map of construction project districts

Under Construction

Interstate 95 / Route 630 (Courthouse Road) Interchange Relocation and Route 630 Widening

Project at a Glance

Begin Date
July 10, 2017

Est Completion Date
July 31, 2020

Phase
Construction

Cost
Interchange is estimated at $149.4 million and Route 630 widening is estimated at $35.9 million

Contractor
Shirley Contracting Co. LLC

Locality
Stafford

District
Fredericksburg

Contact
Kevin Krushinski, VDOT Construction Manager
540-899-4288
Kelly Hannon, Communications Manager
540-374-3344

About the Project

Construction began in July 2017 to rebuild the I-95 interchange at Exit 140 (Route 630 / Courthouse Road) in Stafford County as a diverging diamond interchange. 

Drivers will continue to use the existing Exit 140 interchange until the end of construction by July 2020.

This project will relocate the Exit 140 interchange slightly south of the existing interchange. New overpasses will carry Courthouse Road traffic over Interstate 95.

The project will also relocate the intersection of Courthouse Road and Route 1 to the south to align with Hospital Center Boulevard.

Courthouse Road will be widened to four lanes between Route 1 and I-95. West of I-95, Courthouse Road will be widened to four lanes to just west of Ramoth Church Road / Winding Creek Road. 

A temporary traffic signal and pedestrian crossing was installed at the entrance to Colonial Forge High School and the Liberty Knolls subdivision before the start of the 2017 - 18 school year.

A permanent traffic signal will be installed at the end of the project.

Construction will also realign Ramoth Church Road and Winding Creek Road to intersect at a traffic signal.

Construction Is Underway

Drivers can expect lanes to stay open on Courthouse Road during morning and evening rush hour to minimize delays at peak travel times.

Single lane closures will be scheduled at midday and overnight.

Drivers should consider adding several minutes of travel time when leaving for work or school.

Travelers can expect to see construction equipment and signs, temporary lane markings and traffic shifts.

To receive emails with project news, send an email with "Exit 140 subscribe" in the subject heading to Kelly.Hannon@VDOT.Virginia.Gov.

Work Zone Speed Limit is 35 MPH

The speed limit was reduced to 35 mph on Courthouse Road between Woodcutters Road and Cedar Lane beginning Friday, Aug. 18, 2017.

The speed limit was lowered from 40 mph in the work zone to widen the road from two lanes to four lanes.

The temporary speed limit will be enforced during construction, which is expected to be complete by July 2020.

Traffic Signal Activated At Colonial Forge High School

A temporary traffic signal was activated Wednesday, Aug. 23, 2017, at one of the entrances to Colonial Forge High School and Liberty Knolls Drive. Read more about this signal.

Lane Closures for Monday, April 23 - Friday, April 27, 2018

Work will occur weather permitting.

Interstate 95 Northbound

Tuesday – Wednesday, 9 p.m. 4:30 a.m. Single lane closed overnight near Exit 140. All lanes re-open by 4:30 a.m.

Interstate 95 Southbound

Monday – Tuesday, 10 p.m. 4:30 a.m. Two lanes closed overnight. One lane will re-open by 4:30 a.m. Single lane remains closed until 10 a.m. Tuesday.

Wednesday – Friday, 9 p.m. 10 a.m. Single lane closed overnight near Exit 140, and remains closed until 10 a.m. following morning.

Route 630 (Courthouse Road)

Monday – Thursday, 8:30 a.m. ˗˗ 2 p.m. and Friday, 8:30 a.m. ˗˗ 12 p.m. Courthouse Road will be reduced to one lane from Austin Ridge Drive to Red Oak Drive. Crews will be working near the I-95/Exit 140 interchange.

Monday – Thursday, 8:30 a.m. ˗˗ 2 p.m. and Friday, 8:30 a.m. 12 p.m. Expect alternating, one-way traffic on Courthouse Road between Cedar Lane and Walpole Street for grading and pipe work as part of the widening project.

Ramoth Church Road

Monday – Thursday,  8:30 a.m. ˗˗ 2 p.m. and Friday, 8:30 a.m. 12 p.m. Expect alternating, one-way traffic on Ramoth Church Road between Courthouse Road and Dog Patch Lane. Flaggers will direct drivers in the work zone. Expect brief delays.

Reids Road

Monday – Thursday, 8:30 a.m. 2 p.m. and Friday, 8:30 a.m. noon. Alternating, one-way traffic on Reids Road to allow trucks to enter and exit the work zone.

Snowbird Lane

Monday - Thursday, 8:30 a.m. 2 p.m. and Friday, 8:30 a.m. noon. Expect alternating, one-way traffic on Snowbird Lane at Courthouse Road to allow trucks to enter and exit at the work zone. Flaggers will direct drivers at the intersection. Expect brief delays.

Winding Creek Road

Monday - Thursday,  9 a.m. ˗˗ 2 p.m. and Friday, 9 a.m. noon. Expect alternating, one-way traffic on Winding Creek Road for grading and pipe work as part of the widening project. Flaggers will direct drivers through the work zone. Expect brief delays.

Woodcutters Road

Monday – Thursday,  9 a.m. ˗˗ 2 p.m. and Friday, 9 a.m. 12 p.m. Expect alternating, single lane closures on Woodcutters Road between Courthouse Road and Cutstone Drive. Expect brief delays.

Wyche Road

Monday - Thursday, 8:30 a.m. 2 p.m. and Friday, 8:30 a.m.  noon. Expect alternating, one-way traffic on Wyche Road at Courthouse Road to allow trucks to enter and exit the work zone. Flaggers will direct drivers at the intersection. Expect brief delays.

A full list of weekly lane closures for VDOT's Fredericksburg District (which includes Stafford County) is available at www.VirginiaDOT.org. The list is posted Friday afternoons for the upcoming week.

Clearing Begins for Noise Barrier on I-95 Northbound

Clearing, grading and tree removal began in January 2018 for a new noise barrier along Interstate 95 northbound, north of Courthouse Road. Construction of the noise barrier wall begins in April 2018 and will be finished in August 2018.

Construction Schedule

July 10, 2017: Construction begins on the Courthouse Road widening project west of I-95.

Fall 2017: Construction begins on Exit 140 interchange and Courthouse Road widening east of I-95.

December 20, 2019: Completion of Courthouse Road widening west of I-95.

July 31, 2020: Construction complete on entire project, with the diverging diamond interchange open to traffic.

"Pardon Our Dust" Public Information Meeting: Wednesday, May 17, 2017

A "Pardon Our Dust" public information meeting was held from 6 - 8 p.m. at Colonial Forge High School on Wednesday, May 17, to share details on upcoming construction.

Additional public meetings will be held throughout the project to keep residents informed on our progress.

If you would like to schedule a VDOT speaker to visit your community group to speak about this project, contact VDOT Communications Manager Kelly Hannon at Kelly.Hannon@VDOT.Virginia.Gov. or 540-374-3344.

Pardon Our Dust meeting display board Exit 140 interchange

Pardon Our Dust meeting display board I-95 near Courthouse Road

Pardon Our Dust meeting display board Courthouse Road widening

Pardon Our Dust meeting handout

Pardon Our Dust meeting presentation

Courthouse Road Park and Ride Lot

This project will relocate the VDOT Park and Ride lot on Courthouse Road in Stafford County.

When construction is complete, two new Park and Ride lots will open east of I-95. The lots will have a total of approximately 1,100 parking spaces.

Both Park & Ride lots will be north of the relocated Courthouse Road, on the future Old Courthouse Road (the Courthouse Road currently in use during construction).

The larger lot will have approximately 850 parking spaces and will include a dedicated carpool / vanpool pickup and dropoff area to assist with High Occupancy Vehicle (HOV) use. This lot will also have a dedicated bus dropoff and pickup area.

A smaller lot on the north side of Old Courthouse Road will have an additional, estimated 250 parking spaces.

Current lot users will see no change until late summer/early fall 2018. The existing Park and Ride lot will remain open until that time.

In late summer/early fall 2018, the existing lot will be closed, and users will be shifted to a temporary lot east of I-95 in the same location as the future, permanent lots. The existing 545 parking spaces will be available during construction as the contractor continues work to finish building the permanent lots.

Both parking lots are scheduled to be completed in December 2019, when the diverging diamond interchange at Exit 140 is anticipated to open to traffic. However, the contractor has until July 2020 to complete all work under contract.

VDOT asks that carpools, vanpools and transit riders continue ridesharing from this I-95 interchange during construction.

Diverging Diamond Interchange (DDI)

A diverging diamond interchange (DDI) is an innovative design that is increasingly being used by state transportation departments.

The ramp configuration is similar to a traditional diamond interchange.

However, traffic on the cross street, Courthouse Road, will switch sides.

Traffic is shifted to the left side of the road, which allows vehicles turning left to enter an interstate on-ramp without stopping at a traffic signal.

Frequently asked questions

YouTube simulation of diverging diamond interchange at Interstate 64 and Route 15, Zion Crossroads, Louisa County, Virginia

A traffic analysis, in the form of an Interchange Modification Report, has been performed on the diverging diamond interchange concept.

The findings, approved by the Federal Highway Administration, are below.

Supplement to the Interchange Modification Report

Project Documents

Diverging diamond interchange map: View 1

Diverging diamond interchange map: View 2

Diverging diamond interchange: Preliminary plan

Route 630 widening map: View 1

Route 630 widening map: View 2

Route 630 widening map: View 3

Route 630 widening map: View 4

Route 630 widening map: View 5

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: April 21, 2018