Recently Completed
Route 610, Garrisonville Road |
| Widen Garrisonville Road from four to six lanes |
Project at a Glance
Est Completion Date
June 1, 2009
Locality
Stafford
District
Fredericksburg
June 1, 2009
Locality
Stafford
District
Fredericksburg
Contact
Scott Shropshire
540-374-3317
What's Being Done
Project number 0610-089-168, C502. This project is being constructed to widen Garrisonville Road from four to six lanes. Garrisonville Road carried in excess of 52,000 vehicles per day in 2004 and is anticipated to carry in excess of 85,000 vehicles per day in 2014. Left and right turns are provided throughout the project and three new traffic signals will be added. In addition, modifications will be done to existing signals as needed.
Link to Dashboard
Click this link to DashboardContacts
Scott Shropshire, 540-374-3317Page last modified: Oct. 16, 2006