Five Forks Right Turn Lane Project, Route 5 & Route 615

James City County

Project at a Glance

Begin Date
July 2008

Est Completion Date
Completed September 2008

Cost
$350,000

Contractor
Howard Brothers

Locality
James City

Contact
Lauren Hansen
757-925-2583

About the Project:

The project includes adding dedicated right turn lanes for  Ironbound Road North/South (Route 615) onto Route 5 East/West. The work will overlay the intersection and re-stripe approach lanes for northbound and southbound Ironbound Road.

The dedicated left turn lane on Ironbound Road into the food store Shopping Center will become a dual use left/through lane.

The road will be widened on Ironbound Road in front of the Shopping Center to allow for a dedicated right turn lane from Ironbound Road North onto Route 5 East. Re-striping Ironbound Road will accomidate the additional right turn lane from Ironbound Road South onto Route 5 West.

 

Additional Information:

One lane will remain open in each direction during construction.

Weekly Updates:

To receive weekly updates on VDOT projects around Hampton Roads, please send an email with 'SUBSCRIBE TO VDOT LANE CLOSURES' in the subject line to HamptonRoadsInfo@VDOT.Virginia.gov

Contacts

Lauren Hansen, 757-925-2583
Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects

Page last modified: Nov. 20, 2008