Project at a Glance

Begin Date
August 2007

Est Completion Date
May 2008

Cost
$1.7 Million

Contractor
Howard Brothers Contractor, Inc. from Providence Forge, VA

District
Hampton Roads

Contact
Lauren Hansen
757-925-2583

What's Being Done

This project adds a left turn lane from Jefferson Avenue southbound into Newport News City Center (creating a double left turn at the intersection from Jefferson southbound onto Thimble Shoals). Dedicated right turn lanes from Jefferson northbound onto Thimble Shoals and from Thimble Shoals onto Jefferson northbound will also be created. Additional improvements include installation of sidewalks and pedestrian signal controls.

PDFJEFFERSON AVE AT THIMBLE SHOALS BLVD PROJECT COMPLETE

Impact on Traffic

To help alleviate traffic congestion, there will NOT be any no normally scheduled lane closures on Jefferson Ave. during morning (5:30 a.m. to 9 a.m.) and evening (3:30 p.m. to 6 p.m.) rush hours. Motorists should expect traffic delays and lane shifts throughout the project duration.

Project Updates

To receive weekly updates on VDOT projects around Hampton Roads, please send an email with 'SUBSCRIBE TO VDOT LANE CLOSURES' in the subject line to HamptonRoadsInfo@VDOT.Virginia.gov

Contacts

Lauren Hansen, 757-925-2583
Tom Druhot, 757-253-5367