Intersection Improvements at Route 199 and Brookwood Drive

James City County

Area Maps

Click to view full-size map>

Project Photos



Project at a Glance
Begin Date
March 5, 2018

Est Completion Date
Completed June 2018

Cost
$357,775

Contractor
Henry S. Branscome, LLC

Locality
James City

District
Hampton Roads

Contact
Hampton Roads Communications
757-956-3029

Project Overview

To increase vehicle capacity and alleviate traffic congestion during peak traffic times at the intersection of Route 199 (Humelsine Parkway) and Brookwood Drive in James City County, the following improvements were completed:

Widening of Brookwood Drive:

The previous lane configuration on Brookwood Drive at the intersection of Route 199 consisted of one left turn-through lane and one right turn lane. This project converted the existing right turn lane onto Route 199 east to a left-turn/through lane, as well as add a new right-turn lane on Brookwood Drive onto Route 199 east. 

The new lane configuration on Brookwood Drive now consists of one dedicated left-turn lane, one left-turn/through lane and one dedicated right-turn lane onto Route 199. 

Additional Improvements:

  • Median modifications on Route 199
  • Signal head replacement at the intersection
  • Drainage improvements

Current Status:

The $358,000 construction contract was awarded to Henry S. Branscome, LLC, of Williamsburg, VA on November 16, 2017. 

A notice to proceed construction was issued to the contractor on Monday, March 5, 2018, with an estimated completion date of mid-summer 2018.

Project completed, and new intersection configuration opened to the public on June 7, 2018. 