Project at a Glance

Begin Date
Fall 2017

Est Completion Date
Summer 2018

Cost
$3.1 million

Lengths and Limits
From 0.064 mile swest of Route 646 to 0.067 miles east of Route 646, 0.131 miles

Locality
Campbell

District
Lynchburg

Contact
Renard Yeatts
434-856-8258

Brief description

This proposed project is to construct a roundabout at the intersection of Route 24, Village Highway and Route 646, Spring Mill Road/Doss Road in Campbell County. 

The project limits are from 0.064 miles west of Route 646 to 0.067 miles east of Route 646, an approximate length of 0.131 miles. 

During construction through traffic will be maintained at all times for vehicles up to 45 feet in length, including school buses. 

 

December 10, 2015 Design Public Hearing