In Design: Sudley Manor Drive and Seymour Road Traffic Signal in Prince William County

Cost and schedule ►

This project will install a traffic signal at the intersection of Sudley Manor Drive and Seymour Road. Plans also include pedestrian improvements.

Estimated Costs
Preliminary Engineering - $55,000
Right of Way Acquisition and Utility Relocation - $102,000
Construction - $503,000
Total - $660,000

This project is being financed with federal Highway Safety Improvement Program funds.

At the intersection, Sudley Manor Drive averages up to 33,000 vehicles a day and Seymour Road averages 5,100.

Benefits 

This project aims to improve operations and safety.

Major Milestones 

Notice of Willingness to Hold a Public Hearing - December 2018
Design Approval - March 2019
Begin Right of Way Acquisition - Summer 2019
Begin Construction - Spring 2020

Resources

Contact Info:

Calvin Britt, P.E.
Location & Design

Angel Tao, P.E.
Preliminary Engineering

Major funding source: Highway Safety Improvement Program

Phase: In Design

UPC: 111874

State ID: 1566-076-S53, P101, R201, C501

Federal ID: HSIP-5A01 (867)

Lat/Long: 38.781554, -77.521097

Locality: Prince William

Page last modified: Sept. 11, 2019