Under Construction: Tysons/Old Meadow Road Bike/Ped Improvements in Fairfax County
Cost and schedule ►
Traffic alerts ►
Public outreach ►
This project, in cooperation with Fairfax County, is building a pedestrian and bicycle bridge and shared-use path in the vicinity of Route 123 and I-495 (Capital Beltway).
Based on results of the preliminary engineering phase of the study, and extensive community outreach and input over the last several years, the "Option 2" alignment was selected for final design.
New Bicycle/Pedestrian Bridge over I-495 and Shared-Use Path from Tysons One Place/Fashion Boulevard to Old Meadow Road/ Provincial Drive
Phase 1
During the first phase of construction, a new bicycle and pedestrian bridge over I-495 is being built along with a ten-foot-wide shared-use path from Tysons One Place and Fashion Boulevard to Old Meadow Road and Provincial Drive via the bridge.
Shared-Use Path along Old Meadow Road from Provincial Drive to Route 123
Phase 2
During the second phase of construction, the shared-use path along Old Meadow Road will be completed from Provincial Drive to Route 123 (Dolley Madison Boulevard).

Estimated Costs
Preliminary Engineering - $2.3 million
Right of Way Acquisition and Utility Relocation - $2.3 million
Construction - $7.7 million
Total - $12.3 million
This project is financed with federal, state and local funding.
Benefits
The project aims to improve bicycle and pedestrian safety and connectivity in the Tysons area.
Major Milestones
Design Public Hearing: June 2018
Environmental Studies Memo Available: August 2018
Design Approval: November 2018
Begin Right of Way Acquisition: November 2019
Advertise for Construction: April 2021
Award Construction Contract - June 2021
Begin Phase 1 Construction: August 2021
Phase 1 Final Completion: Summer 2022
Begin Phase 2 Construction: To be determined as additional funding becomes available
Resources
Donald Angerman, CCM
Construction
703-259-3253
Yusaf Masud, P.E.
Construction
703-259-2973
Other relevant links:
Construction Start News Release - August 2021
Environmental Studies Memo - August 2018
Summary of Public Outreach - June 2018
AM/PM Peak Hour Traffic Counts at Selected Intersections - December 2017
Preliminary Engineering Report - July 2017
Concept Plans - June 2017
The Colonies of McLean Meeting Presentation - March 2017
Re-Evaluation Document - March 2007
I-495 HOT Lanes Record of Decision - June 2006
Final Environmental Impact Study - April 2006
Phase: Under Construction
UPC: 104005
State ID: I495-029-078, P101, R201, C501, B630
Federal ID: CM-495-5 (091), CM-495-5 (092)
Lat/Long: 38.916233, -77.217619
Locality:
Fairfax


