Recently Completed
Buckland Bridge Replacement |
| Route 29 Bridge over Broad Run in Prince William County |
Project Photos
Project at a Glance
Begin Date
December 2007
Est Completion Date
Fall 2008
Cost
$2.8 million (construction only)
Contractor
Flippo Construction Company, Inc. (Forestville, MD)
Locality
Prince William
December 2007
Est Completion Date
Fall 2008
Cost
$2.8 million (construction only)
Contractor
Flippo Construction Company, Inc. (Forestville, MD)
Locality
Prince William
Contact
Chan Basnayake, P.E.
What's Being Done
This project will replace the southbound Route 29 bridge deck and widen the road over Broad Run in Prince William County. The existing southbound bridge will be replaced with offsite-fabricated segments. Crews will also complete substructure concrete repairs and re-align the roadway. This work is scheduled to be complete in fall 2008.
Impact on Traffic
During construction, motorists can expect lane closures during off-peak travel times. There will be no lane closures during rush hours. Nighttime detours will occur over 12 independent nights during the final phase of the project when pre-fabricated segments will be set. Two travel lanes in each direction will be maintained through the duration of the project.Detour maps below. View more information on detour dates in the VDOT
press release.
![]()
Preferred detour (Click to enlarge)
![]()
Detour for local traffic (Click to enlarge)
Contacts