East Spring Street Widening

Herndon Parkway to Fairfax County Parkway in the Town of Herndon

Area Maps

Project at a Glance

Begin Date
Advertise for construction: Summer 2020

Phase
Public Comment Period

Cost
$10.5 million

Lengths and Limits
Herndon Pkwy to Fairfax County Pkwy

Locality
Fairfax

Contact
Hamid Misaghian, P.E.
Location & Design
703-259-1795
Andrew Beacher, P.E.
Preliminary Engineering
703-259-2239

Note: A public information meeting was held Nov. 13. If you were unable to attend, you may still submit comments via e-mail (please reference "East Spring Street Widening" in the subject line) or mail through Monday, Nov. 27.

About the Project

This project will widen East Spring Street from four to six lanes from just west of Herndon Parkway to Fairfax County Parkway. Intersection and sidewalk improvements are also part of the project.  

This project is being financed with federal and state funding, including Smart Scale funding.

Schedule
Public information meeting - Nov. 13, 2017
Public information meeting comment period end - Nov. 27, 2017
Design public hearing - Early 2018
Begin right of way acquisition - Spring 2019
Advertise for construction - Summer 2020

Estimated Costs
Preliminary engineering - $723,000
Right of way acquisition/utility relocation - $4.2 million
Construction - $5.6 million
Total: $10.5 million

Project Numbers
State: U000-235-354, P101
UPC: 105521