Project at a Glance
August 13, 2008
Est Completion Date
October 13, 2009
Cost
$5.45 million
Contractor
Fort Myers Construction Corporation
Locality
Alexandria
District
Northern Virginia
Contact
Mahmud M. Hussain, Resident Administrator
703-383-2730
What's Being Done
VDOT has completed rebuilding the ramp that carries traffic from Duke Street (Route 236) eastbound to I-395 northbound, more than two months ahead of schedule. The truck and bus restriction that had been in place since September 2008 has also been lifted.
Reconstruction of the overpass included a new concrete deck, approach curb, guardrails and new lighting. Read the news release here.
Traffic Impacts
Trucks, buses and RVs accessing northbound I-395 from eastbound Duke Street (VA Route 236) were detoured during construction.
Project Number
PM09-100-197, C501Contacts
Mahmud M. Hussain, Resident Administrator, 703-383-2730Field Contact: Giles Njumbe, Project Manager, 571-722-9578
Field Contact: Larry Tomlinson, Area Construction Engineer, 703-383-2075