I-66 Spot Improvements - Spot 1

Westbound from Fairfax Drive to Sycamore Street in Arlington County

Area Map

Project Photos

Project at a Glance

Begin Date
June 14, 2010

Est Completion Date
December 5, 2011

Cost
$14.2 million

Contractor
The Lane Construction Corporation

Locality
Arlington

District
Northern Virginia

Contact

Charles Mel Harvey
Area Construction Engineer
703-259-3240

Jay Babra
Construction Manager
703-259-2944

Project Number: (FO)0066-000-113, C501 (UPC 78826)

About the Project

To help reduce congestion and increase safety along westbound I-66 inside the Capital Beltway, this project extended the existing acceleration lane from the Fairfax Drive on-ramp (just west of George Mason Drive) to the existing deceleration lane at the Sycamore Street off-ramp (almost 2 miles).

The westbound acceleration and deceleration lane between Fairfax Drive and Sycamore Street were lengthened to form a continuous auxiliary lane between the two ramps. A new 12-foot-wide shoulder was constructed with full-strength pavement capable of carrying traffic during emergencies.

The work also included: sight distance improvements, variable and static message signs, traffic management systems, roadway lighting and landscaping in selected areas. All work will be performed within the existing right-of-way.

Future spot improvements, not part of this contract, are planned between Haycock Road and Westmoreland Street, and between Lee Highway and Glebe Road.

 