Recently Completed
Little River Turnpike Pedestrian Improvements |
| At Beauregard Street in Fairfax County |
Project at a Glance
Begin Date
September 3, 2008
Est Completion Date
November 13, 2008
Cost
$322,730.00
Contractor
A & M Concrete Corporation
Locality
Fairfax
District
Northern Virginia
September 3, 2008
Est Completion Date
November 13, 2008
Cost
$322,730.00
Contractor
A & M Concrete Corporation
Locality
Fairfax
District
Northern Virginia
Contact
Mahmud M. Hussain, Resident Administrator
703-383-2730
About the Project
This project was undertaken to improve safety for pedestrians and motorists at Route 236 and Beauregard Street. The project included installing asphalt, underdrain, curb and gutter, drainage structures, sidewalk, handicap ramps, signalization with pedestrian push buttons, pavement markings and a commuter bus shelter.Contacts
Mahmud M. Hussain, Resident Administrator, 703-383-2730Giles Njumbe, Construction Manager, 571-722-9578
Larry Tomlinson, Area Construction Engineer, 703-383-2075
Page last modified: Nov. 16, 2009