Recently Completed: Poland Road and Edgewater Street Permanent Roundabout in Loudoun County

Cost and schedule ►

Public outreach ►

This project replaced the temporary marked and delineated roundabout at the intersection of Poland Road and Edgewater Street with a permanent single lane roundabout, including a raised center island, raised splitter islands, and curb/gutter along the approaches.

Estimated Costs
Preliminary Engineering - $486,000
Right of Way Acquisition and Utility Relocation - $77,000
Construction - $1 million
Total - $1.6 million

At the intersection, Poland Road averages 5,400 vehicles a day and Edgewater Street averages up to 3,800.

Benefits 

This project aimed to improve safety and operations.

Major Milestones 

First Notice of Willingness to Hold a Public Hearing - June 2016
Second Notice of Willingness to Hold a Public Hearing - November 2016
Advertise for Construction – November 2017
Award Construction Contract - January 2018
Begin Construction - February 2018
"Pardon Our Dust" Meeting - March 2018
Substantial Completion - June 2018
Final Completion - October 2018

Resources

Contact Info:

Raymond Kollack
Construction

Project Photos

UPC: 106942

State ID: 0742-053-127, P101, R201, M501

Federal ID: HSIP-5A01 (701)

Lat/Long: 38.904473, -77.491793

Locality: Loudoun