Map of construction project districts

In Design

Rolling Road Widening

Improvements from Viola Street to Old Keene Mill Road in Fairfax County

Area Maps

Project at a Glance

Begin Date
Phase I Construction:
Fall 2019

Phase II Construction: 2022

Est Completion Date
Phase I: Fall 2020

Phase II: 2024

Phase
In Design

Cost
$51.6 million

Lengths and Limits
Viola St to
Old Keene Mill Rd

Locality
Fairfax

District
Northern Virginia

Contact
Hamid Misaghian, P.E.
Location and Design
703-259-1795
Andrew Beacher, P.E.
Preliminary Engineering
703-259-2239

Note: A Traffic Analysis Report is now available.

About the Project

This project aims to reduce congestion and improve safety by widening Rolling Road (Route 638) from two to four lanes between Viola Street and Old Keene Mill Road.

The project also includes a shared-use path to increase safety for bicyclists, pedestrians and other non-motorized users.

The project is being planned in a phased approach:

Phase I - Old Keene Mill Road intersection improvements
Includes interim improvements by adding a second left turn lane from Rolling Road to westbound Old Keene Mill Road, adding a dedicated right turn lane to eastbound Old Keene Mill Road, upgrading the signal and improving the intersection alignment.  

Phase II -  Widening and other improvements 
Includes widening Rolling Road from two to four lanes between Viola Street and Old Keene Mill Road, signal upgrades, pedestrian and bike facilities and improvements to access management.  

The project team has worked with Fairfax County to consider alternative design options, including the possibility of using underground utilities.

The option including underground utilities was evaluated based on feasibility, potential property impacts, cost and schedule. This option is no longer being pursued due to cost concerns.

If you would like to provide feedback at any time, send comments to meetingcomments@vdot.virginia.gov. Include “Rolling Road Widening” in the subject line.

This project is being financed with federal, state, local and Northern Virginia Transportation Authority funds.

Schedule
Public Information Meeting - June 2016
Public Information Meeting - November 2017
CE Reevaluation Public Notice - February 2018
Design Public Hearing - February 2018
Traffic Analysis Report Available - August 2018
Phase I Begin Right of Way Acquisition - Fall 2018
Phase I Begin Utility Relocation - Spring 2019
Phase I Begin Construction - Fall 2019
Phase I Construction Completion - Fall 2020
Phase II Begin Right of Way Acquisition - Winter 2018/19
Phase II Begin Utility Relocation - Winter 2019/20
Phase II Begin Construction - 2022
Phase II Construction Completion - 2024

Estimated Costs
Engineering Design: $5.9 million
Right of Way Acquisition and Utility Relocation: $17.4 million
Construction: $28.3 million
Total: $51.6 million

Resources

Traffic Analysis Report (August 2018)

Design Public Hearing (February 2018)
Meeting Materials
Displays
Public Notice

Categorical Exclusion Reevaluation (February 2018)
Public Notice

Public Information Meeting (November 2017)
Meeting Materials
Presentation
Displays: Noise Study Location Map | Stormwater Management Plan
Public Notice

Community Outreach Meetings Presentation

Public Information Meeting (June 2016)
Presentation
Brochure and Comment Sheet
Displays: 1 2 3 4 5 6
Public Notice

Project Numbers
State: 0638-029-156, P104, R204, C504
UPC: 5559
Federal: STP-5401 (691)

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: Aug. 21, 2018