In Design: Rolling Road Widening

Cost and schedule ►

Note: The Noise Study is now available. Final Report, Appendices A - C, Appendix Dand Appendix E

This project will widen Rolling Road (Route 638) from two to four lanes between Viola Street and Old Keene Mill Road and includes a shared-use path.

The project is being planned in a phased approach:

Phase 1 - Old Keene Mill Road intersection improvements
Includes interim improvements by adding a second left turn lane from Rolling Road to westbound Old Keene Mill Road, adding a dedicated right turn lane to eastbound Old Keene Mill Road, upgrading the signal and improving the intersection alignment.  

Phase 2 -  Widening and other improvements 
Includes widening Rolling Road from two to four lanes between Viola Street and Old Keene Mill Road, signal upgrades, pedestrian and bike facilities and improvements to access management. 

The project team has worked with Fairfax County to consider alternative design options, including the possibility of undergrounding utilities. This option was evaluated based on feasibility, potential property impacts, cost and schedule. At this time this is no longer being pursued due to cost.

The project is being financed with federal, state and local funding including Northern Virginia Transportation Authority funds.

Benefits 

This project aims to reduce congestion and improve safety for all users.

Major Milestones 

Public Information Meeting - June 2016
Public Information Meeting - November 2017
CE Reevaluation Public Notice - February 2018
Design Public Hearing - February 2018
Phase 1 Begin Right of Way Acquisition - Late Winter 2018/19
Phase 1 Begin Utility Relocation - Spring 2019
Phase 1 Begin Construction - Fall 2019
Phase 1 Construction Completion - Fall 2020
Phase 2 Begin Right of Way Acquisition - Late Winter 2018/19
Phase 2 Begin Utility Relocation - Winter 2019/20
Phase 2 Begin Construction - 2022
Phase 2 Construction Completion - 2024

Estimated Costs
Preliminary Engineering: $5.9 million
Right of Way Acquisition and Utility Relocation: $18.7 million
Construction: $31.6 million
Total: $56.1 million

Resources

Contact Info:

Hamid Misaghian, P.E.
Location and Design

Andrew Beacher, P.E.
Preliminary Engineering

Other relevant links:

Noise Study - February 2019
Final Report, Appendices A - C, Appendix D and Appendix E
Traffic Analysis Report - August 2018
Crosswalk Analysis Report - August 2018

Design Public Hearing - February 2018 (Ad), Meeting Materials and Displays

Categorical Exclusion Reevaluation - February 2018 (Ad)

Public Information Meeting - November 2017 (Ad), Meeting MaterialsPresentation 
Displays: Noise Study Location Map | Stormwater Management Plan

Community Outreach Meetings Presentation - July to October 2016

Public Information Meeting - June 2016 (Ad), BrochureComment Sheet and Presentation 
Displays: 1 2 3 4 5 6

Phase: In Design

UPC: 5559

State ID: 0638-029-156, P104, R204, C504

Federal ID: STP-5401 (691)

Long/Lat: 38.771279, -77.231865

Locality: Fairfax

Page last modified: April 26, 2019