Recently Completed: Route 7 Westbound over Sugarland Run Bridge Rehabilitation in Fairfax County
Cost and schedule ►
Public outreach ►
This project rehabilitated the westbound Route 7 (Leesburg Pike) bridge over Sugarland Run. The bridge was originally built in 1947 and widened in 2000.
The improvements included:
- A new concrete bridge deck.
- Bridge pier and abutment repairs.
- Guardrail upgrades and new curb and gutter in the area of the bridge.
The project originally called for further improvements including widening the bridge and extending the acceleration lane from the Fairfax County Parkway (Route 286) on-ramp to Dranesville Road (Route 228); however, these components were later removed from the project due to funding constraints.
This section of Route 7 (westbound and eastbound combined) averages 59,000 vehicles a day.
Estimated Costs
Preliminary Engineering - $1.2 million
Construction - $3.1 million
Total - $4.4 million
The project was financed with state and federal State of Good Repair funds used for bridges.
Benefits
This project aimed to improve safety and extend the overall life of the bridge.
Major Milestones
Design Public Hearing - October 2018
Advertise for Construction - June 2020
Construction Contract Awarded - September 2020
Begin Construction - September 2020
Final Completion - April 2021
Resources
Dinesh Singh, P.E., CCM
Construction
703-259-2216
Chan Basnayake, P.E., PMP, CCM
Construction
703-259-2947
Major funding source: State of Good Repair
Phase: Recently Completed
UPC: 104556, 111678
State ID: 0007-029-113, P101; 0007-029-381, B643
Federal ID: STP-PM09 (324); NHPP-5B01 (139)
Lat/Long: 39.013248, -77.368648
Locality:
Fairfax