Map of construction project districts

Under Construction

Courthouse Road Roundabout installation

At the intersection of Courthouse Road and Allin Road (near Ft. Lee)

Area Map

Project Photos

Project at a Glance

Begin Date
Sept. 2009

Est Completion Date
August 2010

Cost
Approximately $854,000

Lengths and Limits
Intersection of Courthouse Road (Route 106) and Allin Road (Route 634) near Fort Lee

Contractor
Blakemore Construction Corporation

Locality
Prince George

District
Richmond

Contact
Public Affairs
804-524-6094

Project Details

This project will amend the existing signalized intersection located at Courthouse Road and Allin Road (near Ft. Lee) to a roundabout. The project will also install a sidewalk and resurface the road. Temporary signals will also be installed to control traffic during the construction process.The project began Sept. 2009 with an estimated completion date by August 2010. August 19, 2009 News Release

 

Why Does the Intersection Need to be Reconstructed?

The roundabout is being installed to reduce the number of traffic accidents and fatalities at this intersection.

Traffic Impacts

Motorists can expect delays in this area due to overnight detours on Allin Road and daytime alternating lane closures on both Courthouse Road and Allin Road. Work will take place between 8 a.m. - 2 p.m., then from 6 p.m. - 5 a.m. through August 2010. Detours will only take place during night-time hours and will be clearly posted. Drivers can expect delays.

 

 

Link to Dashboard

Courthouse Road Roundabout Installation Project

Contacts

Public Affairs, 804-524-6094
Fort Lee Public Affairs Office, (804) 734-6174
Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects

Page last modified: Oct. 19, 2009