Map of construction project districts

Under Construction

Intersection Improvements at Courthouse and Laurel Spring Roads in Prince George

Turn lanes and new traffic signals to provide improved safety and traffic flow

Project at a Glance

Begin Date
August 2017

Est Completion Date
Winter 2017-18

Phase
Under construction

Cost
$1.1 million

Contractor
J.R. Caskey, Inc.

Locality
Prince George

District
Richmond

Contact
Ron Hobson, P.E.
804-862-6450

Project Description

Crews will construct a northbound right turn lane on Courthouse Road (Route 106) to Laurel Spring Road (Route 616) and replace the intersection’s traffic signals to accommodate the new travel movement. The work will improve safety and traffic flow at this busy local intersection.

 

Traffic Impacts

Alternating daytime lane closures are expected from 8 a.m.-3 p.m.

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: Aug. 22, 2017