Map of construction project districts

Recently Completed

Intersection Improvements near St. Joseph's Villa

Improvements at the intesections of Route 1/Villa Park and St. Joseph's Villa

Project Photos

Project at a Glance

Begin Date
Spring 2017

Est Completion Date
Summer 2017

Cost
$2 million

Locality
Henrico

District
Richmond

Contact
Brian Ramsey, P.E., Area Construction Engineer
(804) 585-3579

What's Being Done?

This project will improve the safety and mobility of pedestrians and vehicular traffic in the form of traffic signal upgrades, curb ramp reconstruction and crosswalks/markings.

The work will provide enhanced safety and better connectivity for local businesses and the St. Joseph's Villa community.

There are areas within the project limits where the pedestrian access routes do not meet current Americans with Disabilities Act (ADA) and Virginia Department of Transportation (VDOT) standards. Also, the existing traffic signals in the project limits have exceeded their life expectancy and are in need of replacement. These improvements are a second phase to the recently completed VDOT roadway improvement project.

Traffic impacts

Minimal lane closures are expected as part of this work. The work began Monday, March 13.

Public Involvement

An information meeting was held on September 10, 2014 at the St. Joseph’s Villa Gym. The information meeting fact sheet is available.