Route 1 improvements - Ashland

Completed ahead of schedule and under budget

Area Map

Project at a Glance

Begin Date
Jan. 2008

Est Completion Date
Dec. 19, 2008 (four months ahead of schedule)

Cost
$2.17 million (approx. $32,000 under budget)

Lengths and Limits
1,500 feet or 0.4 miles

Contractor
Blakemore Construction Corp.

District
Richmond

Contact
VDOT Ashland Residency
(804) 752-5511

What's being done?

VDOT installed safety features to north and southbound Rt. 1 between England Street and Pleasant Street (approximately 1,500 feet or 0.4 miles) to include a new median, turn lanes, sidewalks and traffic signals. The project also included improvements to the road surface, utilities and drainage.

 

Contacts

VDOT Ashland Residency, (804) 752-5511