Map of construction project districts

Recently Completed

Colonial Avenue - Wonju Street -- City of Roanoke

Addressing congestion issues

Project at a Glance

Begin Date
Fall 2007

Est Completion Date
November 2008

Cost
$2.2 million

Contractor
W-L Construction and Paving

Locality
Roanoke

District
Salem

Contact
Salem Public Affairs
540-387-5320

Project Updates

A contract for traffic and safety improvements on Wonju Street was awarded to W-L Construction and Paving from Chilhowie in fall 2007.  The $2.2-million project was completed by November 2008.

Features

The project involved coordinating the signals on Colonial Avenue at Wonju Street to allow for better traffic flow through both intersections.  In addition, construction also included:

  • Constructing a left turn lane from Brandon Avenue onto 23rd Street
  • Installing a new signal at the intersection of Brandon Avenue and 23rd Street
  • Replacing and coordinating the three existing signals along Colonial Avenue between Wonju Street and Brandon Avenue
  • Reconfiguring the existing lanes along Colonial Avenue to include two southbound through lanes and a southbound turn lane between the southbound Route 220 exit ramp and the southbound Route 220 entry ramp
  • Making northbound Colonial Avenue one lane between the southbound Route 220 entry ramp and the southbound Route 220 exit ramp
  • Creating an additional left turn lane from Colonial Avenue onto Brandon Avenue
  • Constructing a designated right turn lane from Colonial Avenue onto Wonju Street
  • Building an additional left turn lane from the southbound Route 220 exit ramp onto Colonial Avenue
  • Restricting access to 23rd Street from Colonial Avenue to right in and right out only

Background

The Problem:
The increasing traffic volumes and resulting congestion in and around the intersections of Colonial Avenue and Wonju Street and the southbound off-ramp from Route 220 (Roy L. Weber Expressway) to Colonial Avenue demonstrated the need to improve traffic flow in this area.

A Solution:
The increasing traffic volumes and congestion prompted the City of Roanoke and VDOT to develop three alternatives to improve the traffic flow in this area.  The three alternatives were presented to the public at citizen information meeting held in October 2005.  Two alternatives involved constructing new sections of roadway while the third alternative called for intersection improvements and signal timing changes to improve traffic flow. VDOT moved forward with the third alternative which offered a way to alleviate congestion using primarily the existing right of way and at a much lower cost than constructing new sections of roadway.  In addition, the public overwhelmingly supported the third alternative.  

 


 

Contacts

Salem Public Affairs, 540-387-5320
Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects

Page last modified: Dec. 4, 2008