Recently Completed
Shenandoah County - Route 263 (Orkney Grade) |
Project at a Glance
Begin Date
Contract awarded on June 17, 2008
Est Completion Date
October 31, 2008
Cost
Contract award: $401,235.82
Lengths and Limits
Just east of Route 721
Contractor
W.L. Construction and Paving, Inc. of Chilhowie
Locality
Shenandoah
District
Staunton
Contract awarded on June 17, 2008
Est Completion Date
October 31, 2008
Cost
Contract award: $401,235.82
Lengths and Limits
Just east of Route 721
Contractor
W.L. Construction and Paving, Inc. of Chilhowie
Locality
Shenandoah
District
Staunton
Contact
Ben Lineberry, P. E.
(540) 434-2586
Project Details
he project on Route 263 in Shenandoah County added a paved shoulder with curb and gutter in a narrow area. A rock slope was removed as part of the project to allow room for the shoulder widening. This location is just east of Route 721.
Benefits
Completion of this project should greatly improve safety in this area.
Contacts
Ben Lineberry, P. E., (540) 434-2586Page last modified: Jan. 22, 2009