Map of construction project districts

Under Construction

Shenandoah County – Route 675 – Stoney Creek Bridge

Project Photos

Project at a Glance

Begin Date
Construction Contract Awarded January 27, 2017

Est Completion Date
Spring 2018

Cost
Contract Value $1,319,720.02

Lengths and Limits
0.07-mile long From: 2.33 Mile North of Route 682 To: 0.33 Mile South of Route 42

Contractor
Kanawha Stone Company Inc., Nitro, W.Va.

Locality
Shenandoah

District
Staunton

Contact
Robert Good, P.E.
540-743-1420

Project Details

This project is located on Route 675 (Stoney Creek Road) in Shenandoah County west of the Town of Edinburg, between Interstate 81 and Route 42.  The bridge over Stoney Creek will be replaced with a new structure.  The current bridge was built in 1932 and has reached the end of its service life. 

The existing bridge is a single lane structure with raised curb and no railing. Route 675 in this location has 10-foot to 11-foot wide lanes with no shoulders

The existing single lane bridge will be replaced with a new, two-lane structure in approximately the same location. The new bridge is approximately 30-feet wide and 105-feet long. Both approaches will consist of two, 11-foot lanes with 3-foot shoulders.

This 0.07-mile long project extends from 2.33-miles north of Route 682 to 0.33-mile south of Route 42. The project is a bridge replacement project with roadway improvements to connect to existing roadway, no additional improvements are proposed. 

The current average daily traffic volume is 580 vehicles per day. This number is projected to be 600 vehicles per day by the year 2038.

The total estimated cost for this project is $2 million, including $307,507 for preliminary engineering, $80,320 for right of way and $1.616 million for construction.

Project Location (latitude, longitude): 38.870278, -78.630556

Notice

Willingness to Hold Public Hearing – Comment due date is October 01, 2014.

What’s Next

Project plan approval  Summer 2015
Right of Way  Summer 2015
Construction advertisement  Fall 2016

Benefits of Project

This project improves safety on Route 675 by replacing a deteriorating bridge structure with a new bridge that is able to support modern traffic both in volume and vehicle weights.  Replacing the bridge avoids the eventual closure of the existing structure, which would lead to a detour of several miles and inconveniencing nearby residences.

During Project Construction

In April 2017 the bridge was closed during construction. A detour will be provided and signed appropriately.

Traffic Alerts

Route 675 (Stoney Creek Road) – Road closed for bridge replacement at Stoney Creek. Work zone in Columbia Furnace area, about five miles north of Edinburg and 0.33-mile south of Route 42 (Senedo Road). Follow posted detours. Estimated completion Spring 2018.

Traffic alerts can also be found on the VDOT website under Travel Center, Travel advisories and lane closures. Click on the area of the state you are interested in, and view current travel advisories and lane closures. Click here to go to the Staunton District Travel Center page:  Staunton District

Real-time traffic information is available on the VDOT 511Virginia.org website and also by calling 511 on your landline or wireless phone.  Click here to go to 511:  Virginia 511 Web

The VDOT Staunton District Twitter feed is at @VaDOTStaunton.

Project Numbers

State  0675-085-748, P101, R201, B666

Federal  ARRA-FS09(182), FH-206(109), FH-206(110)

UPC  97282