Recently Completed
Warren County - Route 661 (Fairground Road) |
Project at a Glance
Begin Date
Contract awarded on July 31, 2008
Est Completion Date
Completion date: October 31, 2008
Cost
Contract award: $159,445.00
Contractor
General Excavation, Inc. of Warrenton
Locality
Warren
District
Staunton
Contract awarded on July 31, 2008
Est Completion Date
Completion date: October 31, 2008
Cost
Contract award: $159,445.00
Contractor
General Excavation, Inc. of Warrenton
Locality
Warren
District
Staunton
Contact
Ben Lineberry, P. E.
(540) 434-2586
Project Details
The project increased the turning area for trucks at the Route 340/522 (Winchester Road) intersection with Route 661 (Fairground Road) in Warren County.Route 661 was also widened to 32 feet in the eastward direction to allow room for future dual left-turn lanes turning onto Route 661 from Route 340/522.
The fairground entrance was also moved east a short distance to enhance safety at this entrance.
The right turn lane on Route 340/522 onto Route 661 was extended and is now 300 feet long to increase truck traffic capacity.
Contacts
Ben Lineberry, P. E., (540) 434-2586Page last modified: Jan. 22, 2009